MISTAKES WITH PANEL BUILD AND LACK OF DRAWINGS

Summary

Logged Date
2026-03-25
Owner
Rob Preston
Party
LME
Area
Panel builds
Priority
Standard
Resolved Date
2026-05-05
Signed Off By
Rob Preston

Problem

Links missing , telemetry terminals wrong way round , no drawings

Investigation And Action

Corrective Action

Feedback sent to supplier; FAT/test evidence reviewed with supplier.

Customer Feedback

-

Root Cause

Supplier delivered incomplete/incorrect build and missing documentation; internal QA needed to verify FAT and drawings.

Preventative Action

Ensure purchase orders specify required drawings and FAT as minimum; supplier feedback loop established.

Review Effectiveness

Supplier engaged and corrective feedback issued; team concluded close.

Status Update

Use this panel for all status changes. Main edit form does not change status.

Status History
FromToChanged AtByNote
In ReviewResolved2026-05-05 21:11:19management reviewTranscript summary: Panel build issues (missing links, telemetry terminals, no drawings). Feedback was provided to supplier and FAT records reviewed; team agreed to close once supplier feedback confirmed. Closed after supplier feedback and FAT review. Root cause check: strong - Direct supplier quality/delivery issues identified and supplier engaged with QA evidence review; actions completed to supplier feedback stage.
InitialIn Review2026-03-30 09:37:54anonymous-
-Initial2026-03-26 18:08:51anonymous-