Projects / INSTALL - Andrew Taylor - STP Install - Swainsley Farm, Chevin Road, Belper, DE56 2US - 07711 141 661, andrew.taylor@artandassociates.co.uk

INSTALL - Andrew Taylor - STP Install - Swainsley Farm, Chevin Road, Belper, DE56 2US - 07711 141 661, andrew.taylor@artandassociates.co.uk

Packaged Treatment Plant / Pump Station project

Status: Active·Sync: Ok·Last synced: 2026-04-13 16:39·Last activity: 2026-02-27 13:01
Summary
Open To-dos
57
Overdue
0
Upcoming Schedule
0
Recent Messages
0
To-do Lists + To-dos

Admin

Open

• N/A - Accommodation
• N/A - Permission to connect to Storm Drain
• Done - Deposit Payment, Invoice: 34272
• N/A - Environment Agency - Application
• Done - Search before you dig
• N/A - Planning Application
• Done - Building Control
• Survey / Site info
+ 10 more

Advanced Booking and Planning

Open

• Order Pump Station
• N/A - Book Electrician
• Done - Book Digger, Dumper & Fuel
• Order Ancillary Materials (pipework etc.)
• ☑ Make parts pack/Pick List - Sent & handed over to Michael 04/09/2025
• Done - Order Concrete, Gravel & Other Bulk
• Order Tanker - Jetter
• Order grab lorry/skip for spoil removal
+ 5 more

On Site

Open

• Done - Photos
• Done - Buildings Control Visit
• Done - Signed RAMS
• Done - Update Tank Board once tank dispatched from Haigh or MPC
• Done - Digger & Dumper etc. OFF HIRE
• Done - Portaloo - OFF HIRE
• 2) Call Chris B. & Andy Lowe to confirm everything is running smoothly
• - Day 1, Customer courtesy call
+ 9 more

Post Install

Open

• Advise customer tank service is due · due 2026-08-03
• Post installation visit - within 3 months
• Done - Update Tank Board as complete once final payment received
• Done - Check payment of final bill, Invoice: - Commission certificate to be send to customer once final balance is paid
• Done - Final email to ensure all has run well & Paperwork
• Done - Final Email to Building Control - Declaration from client & principal contractor
• Done - Electrical Certificate
• Done - Tank Warranty Certificate
+ 8 more
Messages
No mirrored messages yet.
Schedule Entries
No mirrored schedule entries yet.
Documents

WhatsApp Image 2025-09-22 at 09.47.19_33b0997a.jpg

Document · Ruby Birks

WhatsApp Image 2025-09-22 at 09.47.19_2d5a95bb.jpg

Document · Ruby Birks

WhatsApp Image 2025-09-22 at 09.47.19_0b1659de.jpg

Document · Ruby Birks

WhatsApp Image 2025-08-29 at 12.28.31_f59a7997.jpg

Document · Ruby Birks

WhatsApp Image 2025-08-29 at 12.28.30_bad3c964.jpg

Document · Ruby Birks

ufm12_Completion_Certificaten.pdf

Document · Ruby Birks

Warranty Certificate- FujiClean - Andrew Taylor.docx

Document · Ruby Birks

Andrew Taylor Final Declaration Signatures.docx

Document · Ruby Birks

form 2.pdf

Document · Ruby Birks

VID-20250827-WA0008.mp4

Document · Nikoleta Gouzopoulou

WhatsApp Video 2025-09-15 at 19.58.54_5c2398c8.mp4

Document · Nikoleta Gouzopoulou

WhatsApp Video 2025-09-15 at 20.02.25_75edbe06.mp4

Document · Nikoleta Gouzopoulou

VID-20250827-WA0005.mp4

Document · Nikoleta Gouzopoulou

VID-20250827-WA0006.mp4

Document · Nikoleta Gouzopoulou

VID-20250827-WA0007.mp4

Document · Nikoleta Gouzopoulou

IMG-20250924-WA0024.jpg

Document · Nikoleta Gouzopoulou

IMG-20250924-WA0025.jpg

Document · Nikoleta Gouzopoulou

IMG-20250924-WA0026.jpg

Document · Nikoleta Gouzopoulou

IMG-20250925-WA0001.jpg

Document · Nikoleta Gouzopoulou

IMG-20250925-WA0002.jpg

Document · Nikoleta Gouzopoulou

IMG-20250925-WA0003.jpg

Document · Nikoleta Gouzopoulou

IMG-20250925-WA0004.jpg

Document · Nikoleta Gouzopoulou

IMG-20250925-WA0005.jpg

Document · Nikoleta Gouzopoulou

IMG-20250925-WA0006.jpg

Document · Nikoleta Gouzopoulou

IMG-20250925-WA0007.jpg

Document · Nikoleta Gouzopoulou

Recent Activity
Advise customer tank service is due
2026-02-27 13:01 · Todo
Advise customer tank service is due
Post Install
2026-02-27 13:01 · Todolist
Post installation visit - within 3 months
2025-12-04 12:37 · Todo
Post installation visit - within 3 months
Done - Update Tank Board as complete once final payment received
2025-11-12 10:41 · Todo
Done - Update Tank Board as complete once final payment received
Done - Check payment of final bill, Invoice: - Commission certificate to be send to customer once final balance is paid
2025-11-12 10:41 · Todo
Done - Check payment of final bill, Invoice: - Commission certificate to be send to customer once final balance is paid
Done - Final email to ensure all has run well & Paperwork
2025-11-12 10:41 · Todo
Done - Final email to ensure all has run well & Paperwork
Done - Photos
2025-11-12 10:40 · Todo
Done - Photos
On Site
2025-11-12 10:40 · Todolist
Done - Buildings Control Visit
2025-11-12 10:40 · Todo
Done - Buildings Control Visit
Done - Signed RAMS
2025-11-12 10:40 · Todo
Done - Signed RAMS
WhatsApp Image 2025-09-22 at 09.47.19_33b0997a.jpg
2025-11-12 10:40 · Ruby Birks · Document
WhatsApp Image 2025-09-22 at 09.47.19_2d5a95bb.jpg
2025-11-12 10:40 · Ruby Birks · Document
WhatsApp Image 2025-09-22 at 09.47.19_0b1659de.jpg
2025-11-12 10:40 · Ruby Birks · Document
WhatsApp Image 2025-08-29 at 12.28.31_f59a7997.jpg
2025-11-12 10:40 · Ruby Birks · Document
WhatsApp Image 2025-08-29 at 12.28.30_bad3c964.jpg
2025-11-12 10:40 · Ruby Birks · Document
Done - Update Tank Board once tank dispatched from Haigh or MPC
2025-11-12 10:39 · Todo
Done - Update Tank Board once tank dispatched from Haigh or MPC
Order Ancillary Materials (pipework etc.)
2025-11-12 10:37 · Todo
Order Ancillary Materials (pipework etc.)
N/A - Book Electrician
2025-11-12 10:37 · Todo
N/A - Book Electrician
Done - Order Portaloo
2025-11-12 10:37 · Todo
Done - Order Portaloo
Order Telemetry - where applicable
2025-11-12 10:37 · Todo
Order Telemetry - where applicable
Order grab lorry/skip for spoil removal
2025-11-12 10:37 · Todo
Order grab lorry/skip for spoil removal
Order Tanker - Jetter
2025-11-12 10:37 · Todo
Order Tanker - Jetter
Order Pump Station
2025-11-12 10:37 · Todo
Order Pump Station
☑ Order Treatment Tank - FujiClean CEN10 gravity - Allocated to TTB - MLV carriers Delivery, Monday 22/09/2025
2025-11-12 10:37 · Todo
☑ Order Treatment Tank - FujiClean CEN10 gravity - Allocated to TTB - MLV carriers Delivery, Monday 22/09/2025
Done - Order Concrete, Gravel & Other Bulk
2025-11-12 10:37 · Todo
Done - Order Concrete, Gravel & Other Bulk
☑ Make parts pack/Pick List - Sent & handed over to Michael 04/09/2025
2025-11-12 10:37 · Todo
☑ Make parts pack/Pick List - Sent & handed over to Michael 04/09/2025
Done - Book Digger, Dumper & Fuel
2025-11-12 10:37 · Todo
Done - Book Digger, Dumper & Fuel
Advanced Booking and Planning
2025-11-12 10:37 · Todolist
N/A - Accommodation
2025-11-12 10:37 · Todo
N/A - Accommodation
N/A - Permission to connect to Storm Drain
2025-11-12 10:37 · Todo
N/A - Permission to connect to Storm Drain
N/A - Section 106 application
2025-11-12 10:37 · Todo
N/A - Section 106 application
N/A - Section 50 application
2025-11-12 10:37 · Todo
N/A - Section 50 application
N/A - Environment Agency - Application
2025-11-12 10:37 · Todo
N/A - Environment Agency - Application
N/A - Planning Application
2025-11-12 10:37 · Todo
N/A - Planning Application
Done - Final scope of works and sketches agreed with customer
2025-11-12 10:37 · Todo
Done - Final scope of works and sketches agreed with customer
Done - Handover info for lead
2025-11-12 10:37 · Todo
Done - Handover info for lead
Done - Reviewing all project aspects with lead engineer
2025-11-12 10:37 · Todo
Done - Reviewing all project aspects with lead engineer
Done - MPC Commissioning - ask Rob and arrange with Servicing team - if applicable
2025-11-12 10:37 · Todo
Done - MPC Commissioning - ask Rob and arrange with Servicing team - if applicable
Done - Building Control
2025-11-12 10:37 · Todo
Done - Building Control
Done - RAMS
2025-11-12 10:37 · Todo
Done - RAMS