Projects / Jim Wardle - 30 pop STP Install - Enabling Futures, Manchester Road, Hollingworth, Hyde SK14 8LA, UK - 07747465634, jpwardle@outlook.com

Jim Wardle - 30 pop STP Install - Enabling Futures, Manchester Road, Hollingworth, Hyde SK14 8LA, UK - 07747465634, jpwardle@outlook.com

Packaged Treatment Plant / Pump Station project

Status: Active·Sync: Ok·Last synced: 2026-04-13 16:45·Last activity: 2026-02-27 13:03
Summary
Open To-dos
56
Overdue
0
Upcoming Schedule
0
Recent Messages
0
To-do Lists + To-dos

Admin

Open

• Done - MPC Commissioning - ask Rob and arrange with Servicing team - if applicable
• Done - Handover info for lead
• Done - Search before you dig
• Done - Building Control
• Done - RAMS
• Final scope of works and sketches agreed with customer
• N/A - Accommodation
• Done - Deposit Payment, Invoice:
+ 9 more

Advanced Booking and Planning

Open

• Done - Book Ground-workers - Add Synchro ticket - CBs Invoice sent to Lee 03/09/2025
• Done - Check Sub-Contractors insurance (in date correct level of cover)
• Done - Book Digger, Dumper & Fuel
• Order Ancillary Materials (pipework etc.)
• Done - Make parts pack/Pick List
• Done - Order Concrete, Gravel & Other Bulk
• Done - Order Treatment Tank - Add & allocate tank to Tank Board (if tank is located at Haigh) or Allocate tank to customer on Tank Board (if tank is located at MPC)
• N/A - Book Electrician
+ 5 more

On Site

Open

• N/A - Buildings Control Visit
• Done - Digger & Dumper etc. OFF HIRE
• Done - Photos
• Done - Call Chris B. & Andy Lowe to confirm everything is running smoothly
• Done - Call customer to check all is well
• Client sign off
• Done - Signed RAMS
• Done - Start Synchro ticket
+ 9 more

Post Install

Open

• Advise customer tank service is due · due 2026-07-01
• DONE - Service paperwork
• Post installation visit - within 3 months
• Done - Update Tank Board as complete once final payment received
• Commission Certificate - to be retained until final balance is paid.
• Done - Check payment of final bill, Invoice: ST-35049
• Done - Final Email to Building Control - Declaration from client & principal contractor
• Done - Electrical Certificate
+ 8 more
Messages
No mirrored messages yet.
Schedule Entries
No mirrored schedule entries yet.
Documents

2025 - SSC Standard Service Agreements Enabling Futures 30 Pop .pdf

Document · Helen

2025 - SSC Standard Service Agreements Enabling Futures 30 Pop .docx

Document · Helen

Job_Post Installation Check - MARSH ENSIGN 30 .pdf

Document · Ruby Birks

Screenshot 2025-11-12 102018.png

Document · Ruby Birks

Screenshot 2025-10-17 135323.png

Document · Ruby Birks

Commission Certificate - Enabling Futures 30 PE.pdf

Document · Helen

2025 - SSC Standard Service Agreements with Tank Empty Enabling Futures 16 and 30 Pop.pdf

Document · Ruby Birks

2025 - SSC Standard Service Agreements with Tank Empty Enabling Futures 16 and 30 Pop.docx

Document · Ruby Birks

2025 - SSC Standard Service Agreements with Tank Empty Enabling Futures 30 Pop.pdf

Document · Ruby Birks

2025 - SSC Standard Service Agreements with Tank Empty Enabling Futures 30 Pop.docx

Document · Ruby Birks

FULL (E3.1.1) FORM 5 Full_Part Final Certificate 2024. (Duty Holder Copy) - AIMA-25-87251-DOM.pdf

Document · Ruby Birks

TankWarranty30pop.pdf

Document · Ruby Birks

FULL (E3.1.1) FORM 5 Full_Part Final Certificate 2024. (Duty Holder Copy) - AIMA-25-87251-DOM.pdf

Document · Ruby Birks

Minor Works_Ref98495019.pdf

Document · Ruby Birks

IMG-20250827-WA0007.jpg

Document · Ruby Birks

IMG-20250827-WA0008.jpg

Document · Ruby Birks

IMG-20250827-WA0009.jpg

Document · Ruby Birks

IMG-20250827-WA0010.jpg

Document · Ruby Birks

IMG-20250829-WA0063.jpg

Document · Ruby Birks

IMG-20250829-WA0064.jpg

Document · Ruby Birks

IMG-20250829-WA0065.jpg

Document · Ruby Birks

IMG-20250829-WA0066.jpg

Document · Ruby Birks

IMG-20250829-WA0067.jpg

Document · Ruby Birks

IMG-20250829-WA0068.jpg

Document · Ruby Birks

IMG-20250829-WA0069.jpg

Document · Ruby Birks

Recent Activity
Advise customer tank service is due
2026-02-27 13:03 · Todo
Advise customer tank service is due
Post Install
2026-02-27 13:03 · Todolist
2025 - SSC Standard Service Agreements Enabling Futures 30 Pop .pdf
2026-02-12 11:30 · Helen · Document
2025 - SSC Standard Service Agreements Enabling Futures 30 Pop .docx
2026-02-12 11:30 · Helen · Document
DONE - Service paperwork
2026-02-12 11:30 · Todo
DONE - Service paperwork
Job_Post Installation Check - MARSH ENSIGN 30 .pdf
2026-02-11 09:31 · Ruby Birks · Document
Post installation visit - within 3 months
2026-02-11 09:31 · Todo
Post installation visit - within 3 months
Done - Book Ground-workers - Add Synchro ticket - CBs Invoice sent to Lee 03/09/2025
2025-11-12 10:24 · Todo
Done - Book Ground-workers - Add Synchro ticket - CBs Invoice sent to Lee 03/09/2025
Advanced Booking and Planning
2025-11-12 10:24 · Todolist
Done - Check Sub-Contractors insurance (in date correct level of cover)
2025-11-12 10:24 · Todo
Done - Check Sub-Contractors insurance (in date correct level of cover)
Done - Book Digger, Dumper & Fuel
2025-11-12 10:24 · Todo
Done - Book Digger, Dumper & Fuel
Order Ancillary Materials (pipework etc.)
2025-11-12 10:24 · Todo
Order Ancillary Materials (pipework etc.)
Done - Make parts pack/Pick List
2025-11-12 10:24 · Todo
Done - Make parts pack/Pick List
Done - Order Concrete, Gravel & Other Bulk
2025-11-12 10:24 · Todo
Done - Order Concrete, Gravel & Other Bulk
Done - Order Treatment Tank - Add & allocate tank to Tank Board (if tank is located at Haigh) or Allocate tank to customer on Tank Board (if tank is located at MPC)
2025-11-12 10:24 · Todo
Done - Order Treatment Tank - Add & allocate tank to Tank Board (if tank is located at Haigh) or Allocate tank to customer on Tank Board (if tank is located at MPC)
Screenshot 2025-11-12 102018.png
2025-11-12 10:20 · Ruby Birks · Document
Done - Update Tank Board as complete once final payment received
2025-10-17 16:07 · Todo
Done - Update Tank Board as complete once final payment received
Commission Certificate - to be retained until final balance is paid.
2025-10-17 13:53 · Todo
Commission Certificate - to be retained until final balance is paid.
Screenshot 2025-10-17 135323.png
2025-10-17 13:53 · Ruby Birks · Document
Done - Check payment of final bill, Invoice: ST-35049
2025-10-17 13:53 · Todo
Done - Check payment of final bill, Invoice: ST-35049
Commission Certificate - Enabling Futures 30 PE.pdf
2025-10-17 13:51 · Helen · Document
Snags
2025-10-17 13:51 · Todo
Snags
Customer Feedback
2025-10-17 13:51 · Todo
Customer Feedback
Final email to ensure all has run well & Paperwork
2025-10-17 13:51 · Todo
Final email to ensure all has run well & Paperwork
Done - Final Email to Building Control - Declaration from client & principal contractor
2025-10-17 13:51 · Todo
Done - Final Email to Building Control - Declaration from client & principal contractor
End of job call to installation lead / Improvement Review
2025-10-17 13:51 · Todo
End of job call to installation lead / Improvement Review
Done - Electrical Certificate
2025-10-17 13:51 · Todo
Done - Electrical Certificate
2025 - SSC Standard Service Agreements with Tank Empty Enabling Futures 16 and 30 Pop.pdf
2025-10-08 12:08 · Ruby Birks · Document
2025 - SSC Standard Service Agreements with Tank Empty Enabling Futures 16 and 30 Pop.docx
2025-10-08 12:08 · Ruby Birks · Document
2025 - SSC Standard Service Agreements with Tank Empty Enabling Futures 30 Pop.pdf
2025-10-07 14:15 · Ruby Birks · Document
2025 - SSC Standard Service Agreements with Tank Empty Enabling Futures 30 Pop.docx
2025-10-07 14:15 · Ruby Birks · Document
FULL (E3.1.1) FORM 5 Full_Part Final Certificate 2024. (Duty Holder Copy) - AIMA-25-87251-DOM.pdf
2025-09-22 10:55 · Ruby Birks · Document
Done - Tank Warranty Certificate
2025-09-22 10:44 · Todo
Done - Tank Warranty Certificate
TankWarranty30pop.pdf
2025-09-22 10:44 · Ruby Birks · Document
FULL (E3.1.1) FORM 5 Full_Part Final Certificate 2024. (Duty Holder Copy) - AIMA-25-87251-DOM.pdf
2025-09-17 10:06 · Ruby Birks · Document
N/A - Buildings Control Visit
2025-09-17 10:06 · Todo
N/A - Buildings Control Visit
On Site
2025-09-17 10:06 · Todolist
Minor Works_Ref98495019.pdf
2025-09-12 09:14 · Ruby Birks · Document
N/A - Book Electrician
2025-09-12 09:14 · Todo
N/A - Book Electrician
Done - Digger & Dumper etc. OFF HIRE
2025-09-11 11:32 · Todo
Done - Digger & Dumper etc. OFF HIRE
Card Table
No mirrored card-table items yet.