Projects / Dyserth (MG), S-050471, ST-010168

Dyserth (MG), S-050471, ST-010168

1500 ACE Inlet (ex Amble sp41994?)

Status: Active·Sync: Attention·Last synced: 2026-04-24 11:17·Last activity: 2025-12-16 13:12
Summary
Open To-dos
9
Overdue
3
Upcoming Schedule
0
Recent Messages
0
To-do Lists + To-dos

Delivery date: 22-Apr-13 (was 29-Apr-13, was 02-Apr-13, was 11-Mar-13)

Open

Admin Tasks

Open

• Handover · due 2012-12-24
• Upload Customer Requirements · due 2013-04-22
• Payment · due 2013-04-29
• Payment Terms · due 2013-04-29
• Design · due 2013-10-25
• Retention payment date: · due 2014-03-06
• Warranty · due 2014-05-15

Snags - Haigh Responsibility

Open

• Flooring Panel · due 2013-08-13
• LS Feed pipework blocked · due 2013-08-30
• LS issues · due 2013-09-19
• Pict 0910 showing some lagged pipe work that needs finishing off with the outer covering.
• The lifting bolts need removing from the top off the MCC kiosk.
• Pict 0899 showing the floor grating unfinished.
• Pict 0900 showing the task lighting isolation switch and label hidden from view by the pipe and needs repositioning.
• Pict 0898 showing the open channel above the step with no fall protection into the channel.
+ 2 more

Variation Orders / Additional Site Work

Open

Variation Orders / Additional Site Work

Open

Site Reports

Open

• Site Report Bandgritter blockages/Service Exchange M/P · due 2015-08-26
• Site Visit report LS305 and Grit Tumbler Blockage

Photographs

Open

• 30-Jul-13 snaqging
• Health + Safety (w/c 13-May-13)
• LS Failure w/c 13-May-13
• Install photos 26-Apr-13
• Ex Rotherwas 28-Mar-13

Miscellaneous Costs

Open

Messages

LS issues

Unknown · 2013-05-16 08:58

Transport

Unknown · 2013-04-19 09:17

Delivery date: 22-Apr-13 (was 29-Apr-13, was 02-Apr-13, was 11-Mar-13)

Unknown · 2012-12-20 14:17

Schedule Entries
No mirrored schedule entries yet.
Documents

106780-01.pdf

Document · Paul Rollinson

105483-01.pdf

Document · Paul Rollinson

105662-01.pdf

Document · Paul Rollinson

RE Dyserth service 6th March @ 9 am.msg

Document · Ian Blayney

Dyseth signed rams and despatch .msg

Document · Ian Blayney

dyseth note.msg

Document · Ian Blayney

Photos Dyserth.msg

Document · Ian Blayney

Dyserth Bandscreen Bearing RA.doc

Document · Ian Blayney

Dyserth Bandscreen Bearing RA.doc

Document · Ian Blayney

ST-_[Untitled]_2608201508393500.pdf

Document · Mike Greenman

300716-01.pdf

Document · Mike Greenman

300716-01.pdf

Document · Paul Rollinson

Dyserth Manual.pdf

Document · Mike Greenman

LS-Quotation-265729-Mike_Greenman.pdf

Document · Mike Greenman

Document.pdf

Document · Mike Greenman

Document.pdf

Document · Mike Greenman

PJ13.0099 Haigh Eng Dyserth DWG.pdf

Document · Mike Greenman

Dyserth site Visit 22.doc

Document · Mike Greenman

DSCF3009.JPG

Document · Tony Cudok

DSCF3010.JPG

Document · Tony Cudok

PICT0900.JPG

Document · Tony Cudok

PICT0899.JPG

Document · Tony Cudok

PICT0898.JPG

Document · Tony Cudok

PICT0910.JPG

Document · Tony Cudok

PICT0895.JPG

Document · Tony Cudok

Recent Activity
106780-01.pdf
2025-12-16 13:12 · Paul Rollinson · Document
105483-01.pdf
2025-12-16 12:55 · Paul Rollinson · Document
105662-01.pdf
2025-12-16 12:55 · Paul Rollinson · Document
RE Dyserth service 6th March @ 9 am.msg
2018-03-09 12:55 · Ian Blayney · Document
Dyseth signed rams and despatch .msg
2018-03-09 12:40 · Ian Blayney · Document
dyseth note.msg
2018-03-09 12:39 · Ian Blayney · Document
Photos Dyserth.msg
2018-03-09 12:38 · Ian Blayney · Document
Dyserth Bandscreen Bearing RA.doc
2018-03-09 12:33 · Ian Blayney · Document
Dyserth Bandscreen Bearing RA.doc
2018-03-09 12:33 · Ian Blayney · Document
ST-_[Untitled]_2608201508393500.pdf
2015-08-26 09:45 · Mike Greenman · Document
Site Report Bandgritter blockages/Service Exchange M/P
2015-08-26 09:45 · Todo
Site Report Bandgritter blockages/Service Exchange M/P
Site Reports
2015-08-26 09:45 · Todolist
LS issues
2014-08-12 13:34 · Todo
LS issues
Snags - Haigh Responsibility
2014-08-12 13:34 · Todolist
Retention payment date:
2014-06-25 09:35 · Todo
Retention payment date:
Design
2014-06-25 09:35 · Todo
Design
Admin Tasks
2014-06-25 09:35 · Todolist
300716-01.pdf
2014-06-22 19:13 · Mike Greenman · Document
300716-01.pdf
2014-06-22 19:12 · Paul Rollinson · Document
Dyserth Manual.pdf
2014-06-22 19:12 · Mike Greenman · Document
LS-Quotation-265729-Mike_Greenman.pdf
2014-06-22 18:36 · Mike Greenman · Document
Document.pdf
2014-06-22 18:26 · Mike Greenman · Document
Document.pdf
2014-06-22 18:26 · Mike Greenman · Document
PJ13.0099 Haigh Eng Dyserth DWG.pdf
2014-06-22 18:26 · Mike Greenman · Document
Warranty
2014-05-14 12:09 · Todo
Warranty
Handover
2013-09-26 11:37 · Todo
Handover
Dyserth site Visit 22.doc
2013-09-04 12:58 · Mike Greenman · Document
Site Visit report LS305 and Grit Tumbler Blockage
2013-09-04 12:58 · Todo
Site Visit report LS305 and Grit Tumbler Blockage
LS Feed pipework blocked
2013-09-03 08:36 · Todo
LS Feed pipework blocked
Pict 0910 showing some lagged pipe work that needs finishing off with the outer covering.
2013-08-28 12:20 · Todo
Pict 0910 showing some lagged pipe work that needs finishing off with the outer covering.
The lifting bolts need removing from the top off the MCC kiosk.
2013-08-28 12:20 · Todo
The lifting bolts need removing from the top off the MCC kiosk.
Pict 0899 showing the floor grating unfinished.
2013-08-28 12:20 · Todo
Pict 0899 showing the floor grating unfinished.
Pict 0900 showing the task lighting isolation switch and label hidden from view by the pipe and needs repositioning.
2013-08-28 12:20 · Todo
Pict 0900 showing the task lighting isolation switch and label hidden from view by the pipe and needs repositioning.
Pict 0898 showing the open channel above the step with no fall protection into the channel.
2013-08-28 12:20 · Todo
Pict 0898 showing the open channel above the step with no fall protection into the channel.
Pict 0895 shows some spillage and there is more under the unit the unit has a hose reel but and a potable pipe was laid to this but not yet connected this would be an illegal connection and a wash water booster set should have been provided for this for…
2013-08-28 12:20 · Todo
Pict 0895 shows some spillage and there is more under the unit the unit has a hose reel but and a potable pipe was laid to this but not yet connected this would be an illegal connection and a wash water booster set should have been provided for this for the operators/ fitters to…
Cover for Storm O/F Box
2013-08-28 12:05 · Todo
Cover for Storm O/F Box
Flooring Panel
2013-08-20 15:25 · Todo
Flooring Panel
DSCF3009.JPG
2013-08-02 14:32 · Tony Cudok · Document
DSCF3010.JPG
2013-08-02 14:32 · Tony Cudok · Document
30-Jul-13 snaqging
2013-08-02 14:32 · Todo
30-Jul-13 snaqging
Card Table
No mirrored card-table items yet.
Sync History