Booked 14/11/2025 - Advise customer tank service is due
2024-12-17 09:14 · Todo
DONE - Post installation visit - within 3 months
2024-11-22 12:09 · Todo
PAID 22/11/24 Check payment of final bill
Jim Dickinson - Rose Cottage Holiday Cottages, Sutton under Whitestonecliffe, Thirsk YO7 2QA - 07740 948024 - jim.dickinson@btinternet.com INSTALLATION PROJECT · DONE & SENT - Commission Certificate - Dean & Alex install Tricel 8 W/C 11/11/24 £225.00 empty @ £265.00 Helen
2024-11-22 12:08 · Todo
DONE & SENT - Commission Certificate - Dean & Alex install Tricel 8 W/C 11/11/24 £225.00 empty @ £265.00 Helen
2024-11-21 14:00 · Todo
DONE - Final Email to Building Control Received 20/11/24
2024-11-21 09:45 · Todo
DONE - Final email to ensure all has run well & Paperwork
2024-11-20 11:52 · Todo
DONE - Buildings Control Visit - final paperwork sent 19/11/24 just waiting for sign off
2024-11-19 14:58 · Todo
DONE Service paperwork - Dean & Alex install Tricel 8 W/C 11/11/24 £225.00 empty @ £265.00
2024-11-19 11:43 · Todo
DONE - Call customer to check all is well - day one, day three and last day for final call
Jim Dickinson - Rose Cottage Holiday Cottages, Sutton under Whitestonecliffe, Thirsk YO7 2QA - 07740 948024 - jim.dickinson@btinternet.com INSTALLATION PROJECT · NOT REQUIRED - Order grab lorry/skip for spoil removal - Awaiting for instruction from Dean when onsite
2024-11-19 11:43 · Todo
NOT REQUIRED - Order grab lorry/skip for spoil removal - Awaiting for instruction from Dean when onsite
2024-11-19 08:57 · Todo
DONE - Waste Transfer Note(s) for any tankering
2024-11-12 16:19 · Todo
DONE - Order Ancillary Materials (pipework etc.)
2024-11-12 16:19 · Todo
DONE - Order Concrete, Gravel & Other Bulk
2024-11-12 16:18 · Todo
N/A Order Control Panel - Telemetry - where applicable
2024-11-12 16:18 · Todo
DONE - Final scope of works and sketches agreed with customer
2024-11-05 11:13 · Todo
DONE - Book Electrician - Spoke with Chris @ Scope all fine
2024-11-05 11:12 · Todo
N/A - Check Sub-Contractors insurance (in date correct level of cover)
2024-11-05 11:10 · Todo
DONE - SENT 08/10/24 - Introduction email and confirmed date
2024-11-01 10:11 · Todo
DONE 14/10/24 - Order Treatment Tank / Pump Station etc
2024-10-14 10:31 · Todo
DONE - Book Ground-workers- Dean & Alex 11/11/24
2024-10-14 09:19 · Todo
N/A - Permission to connect to Storm Drain
2024-10-07 13:47 · Todo
End of job call to installation lead / Improvement Review