2025-04-02 16:45 · Todo
DONE 12/2/2025 Post installation visit - within 3 months
2025-01-10 09:14 · Todo
N/A Waste Transfer Note(s) for any tankering
Kevin Villiers - GWI UK Holding Limited - Whatley Rail Sidings, Whatley, Frome BA11 3LF - kevin.villiers@gwrr.co.uk - 07716 224522 INSTALLATION PROJECT · DONE Commission Certificate - to be retained until final balance is paid. - Installation of FujiClean CEN5 & SEPS Chris Britland w/c 23/09/24 Sent to Kevin 10/01/25
2025-01-10 09:11 · Todo
DONE Commission Certificate - to be retained until final balance is paid. - Installation of FujiClean CEN5 & SEPS Chris Britland w/c 23/09/24 Sent to Kevin 10/01/25
2025-01-09 13:43 · Todo
DONE - Sent 22/11/24 Final Email to Building Control - check next week - Received 09/01/25
Kevin Villiers - GWI UK Holding Limited - Whatley Rail Sidings, Whatley, Frome BA11 3LF - kevin.villiers@gwrr.co.uk - 07716 224522 INSTALLATION PROJECT · RE_ CM_ FW_ SBC_ 2_BN_24_04403_CBR Freightliner Maintenance Whatley Railhead Shepton Mallet Somerset BA11 3LF.msg
2024-11-27 10:04 · Louise Prince · Document
2024-11-08 09:58 · Louise Prince · Document
2024-11-08 09:58 · Todo
DONE - Order Treatment Tank / Pump Station etc
2024-10-08 12:08 · Todo
DONE - Final email to ensure all has run well & Paperwork
2024-10-01 12:07 · Todo
DONE Service paperwork - Installation of CEN5 & TEPS Chris Britland W/C 23/09/24
2024-09-30 09:30 · Todo
DONE - Book Ground-workers CHRIS BRITLAND 23/09/24
2024-09-27 11:53 · Todo
DONE 27/09/24 Digger & Dumper etc. OFF HIRE
2024-09-27 11:49 · Todo
DONE - Order grab lorry/skip for spoil removal
2024-09-26 08:11 · Todo
DONE ATTENDED 25/09/24 Buildings Control
Kevin Villiers - GWI UK Holding Limited - Whatley Rail Sidings, Whatley, Frome BA11 3LF - kevin.villiers@gwrr.co.uk - 07716 224522 INSTALLATION PROJECT · SBC_ 2_BN_24_04403_CBR Freightliner Maintenance Whatley Railhead Shepton Mallet Somerset BA11 3LF.msg
2024-09-26 08:10 · Louise Prince · Document
Kevin Villiers - GWI UK Holding Limited - Whatley Rail Sidings, Whatley, Frome BA11 3LF - kevin.villiers@gwrr.co.uk - 07716 224522 INSTALLATION PROJECT · Done -Order Concrete,Gravel & Other Bulk - RING AND PAY FOR CONCRETE 01458 830635 (Option 1) JAKE GARDENER
2024-09-25 09:30 · Todo
Done -Order Concrete,Gravel & Other Bulk - RING AND PAY FOR CONCRETE 01458 830635 (Option 1) JAKE GARDENER
2024-09-18 14:34 · Todo
DONE - Final scope of works and sketches agreed with customer
2024-09-10 11:49 · Todo
N/A Permission to connect to Storm Drain
2024-09-10 11:47 · Todo
DONE - Commission - Nimesh attending 27/09/24
2024-09-10 11:26 · Todo
Order Ancillary Materials (pipework etc.)
2024-09-09 11:14 · Todo
DONE - Introduction email and confirmed date
2024-09-09 11:10 · Todo
Order Control Panel - Telemetry - where applicable
2024-09-09 11:10 · Todo
Check Sub-Contractors insurance (in date correct level of cover)
2024-09-09 11:10 · Todo
Call customer to check all is well - day one, day three and last day for final call
2024-09-09 11:10 · Todo
End of job call to installation lead / Improvement Review