2026-01-06 09:34 · Todo
HM emailed 3/7/2025 - Advise customer tank service is due
2025-01-24 12:03 · Todo
DONE Introduction email and confirmed date
2025-01-10 11:04 · Todo
Scheduled 10/1/2025 - Post installation visit - within 3 months
2024-09-12 15:10 · Todo
PAID 12/09/24 Payment of final bill
2024-09-03 10:57 · Todo
N/A - Digger & Dumper etc. OFF HIRE
2024-09-03 10:53 · Todo
Call customer to check all is well - day one, day three and last day for final call
2024-09-03 10:51 · Todo
DONE - Final email to ensure all has run well & Paperwork
2024-08-16 10:51 · Todo
DONE - SHAUN COUPE Book Ground-workers
2024-08-15 17:15 · Louise Prince · Document
2024-08-12 11:51 · Todo
DONE 12/08/24 Search before you dig
2023-12-07 10:25 · Todo
Order Treatment Tank / Pump Station etc
2023-11-29 21:15 · Todo
DONE Final scope of works and sketches agreed with customer
2023-11-27 15:38 · Todo
Order grab lorry/skip for spoil removal
2023-11-27 15:38 · Todo
Order Concrete, Gravel & Other Bulk
2023-11-22 14:10 · Todo
N/A Waste Transfer Note(s) for any tankering
2023-11-22 14:10 · Todo
N/A Permission to connect to Storm Drain
2023-11-22 14:10 · Todo
N/A Environment Agency - Application
2023-09-27 19:50 · Todo
Order Control Panel - Telemetry - where applicable
2023-09-27 19:50 · Todo
Order Ancillary Materials (pipework etc.)
2023-09-27 19:50 · Todo
End of job call to installation lead / Improvement Review