Project Activity

Cross-project Basecamp activity feed for operational visibility.

Sync Admin
2026-01-06 09:34 · Todo
Order Ancillary Materials (pipework etc.)
2022-12-13 15:30 · Todo
DONE GREEN POWER - Book Digger, Dumper & Fuel
2022-12-13 15:30 · Todo
Post installation visit - within 3 months
2021-09-01 11:14 · Todo
n/a - Order Control Panel - Telemetry - where applicable
2021-09-01 11:14 · Todo
Order grab lorry/skip for spoil removal
2021-09-01 11:14 · Todo
DONE Book Ground-workers (Dean & Luke Seedhouse)
2021-09-01 11:14 · Todo
DONE Order Treatment Tank / Pump Station - order Pura Flo unit
2021-09-01 11:14 · Todo
DONE Order Concrete, DONE Limestone, Gravel & Other Bulk
2021-09-01 11:14 · Todo
DONE - Book Digger, Dumper & Fuel for Percolation
2021-06-16 15:54 · Todo
Final email to ensure all has run well & Paperwork
2021-04-07 09:51 · Todo
Percolation Digger & Dumper etc. OFF HIRED
2021-03-15 12:29 · Todo
Final scope of works and sketches agreed with customer
2021-03-15 12:29 · Todo
N/A Permission to connect to Storm Drain
2021-03-15 10:12 · Todo
End of job call to installation lead / Improvement Review