2022-12-13 15:30 · Todo
DONE Order Concrete, DONE Gravel & DONE Other Bulk
2022-09-22 13:49 · Todo
Post installation visit - within 3 months
2021-07-08 11:21 · Kaz Lumb · Document
2021-07-08 11:21 · Todo
Final email to ensure all has run well & Paperwork
2021-07-08 11:21 · Kaz Lumb · Document
2021-07-08 11:13 · Kaz Lumb · Document
2021-07-07 13:54 · Kaz Lumb · Document
2021-07-07 13:54 · Kaz Lumb · Document
2021-07-07 13:48 · Todo
NA Final Email to Building Control
2021-06-30 15:24 · Todo
DONE Order Treatment Tank / Pump Station etc @ Ross
2021-06-24 14:00 · Todo
DONE Book Digger, Dumper & Fuel
2021-06-18 12:02 · Todo
Introduction email and confirmed date
2021-06-17 13:16 · Todo
NA Order grab lorry/skip for spoil removal
2021-06-17 13:16 · Todo
NA Permission to connect to Storm Drain
2021-06-17 13:16 · Todo
NA Environment Agency - Application
2021-06-17 13:16 · Todo
NA Buildings Control - Phil to advise the details of one already on job
2021-06-15 14:27 · Todo
DONE Book Ground-workers - Dean & Luke
2021-06-15 14:21 · Todo
Order Control Panel - Telemetry - where applicable
2021-06-15 14:21 · Todo
Order Ancillary Materials (pipework etc.)
2021-06-15 14:21 · Todo
Waste Transfer Note(s) for any tankering
2021-06-15 14:21 · Todo
Final scope of works and sketches agreed with customer
2021-06-15 14:21 · Todo
Advise customer tank service is due
2021-06-15 14:21 · Todo
End of job call to installation lead / Improvement Review