2026-01-06 09:34 · Todo
Order Ancillary Materials (pipework etc.)
2021-03-31 17:01 · Todo
Skip Off Hire (scheduled to be collected 03.03.21 pm)
2021-03-31 17:01 · Todo
Welfare Unit (toilet & hot and cold running water booked TravsP arriving 01.03.2021)
2021-03-31 17:01 · Todo
Heras Fencing (booked arr. 01.03.2021 at 8am)
2021-03-31 17:01 · Todo
Accommodation (booked 01.03.21 4 nights x 2)
2021-03-31 17:00 · Todo
Order grab lorry/skip for spoil removal (skip booked pay 26.02.21)
2021-03-31 17:00 · Todo
Order Tanker - Jetter (confirmed09:00hrs 1.03.21)
Poole Canoe Club - The PHCC Boathouse, Lake Pier, Lake Dr, Poole BH15 4LR - adrian.oates@phcc.org.uk - 07825 987801- shills7699@aol.com - 07799 082263 · Order Concrete, Gravel & Other Bulk (paid booked for 3rd March 10-12oclock) reinstatement ordered 25.02.21
2021-03-31 17:00 · Todo
Order Concrete, Gravel & Other Bulk (paid booked for 3rd March 10-12oclock) reinstatement ordered 25.02.21
2021-03-31 17:00 · Todo
Book Digger, Dumper & Fuel ( account approved, order confirmed)
2021-03-31 17:00 · Todo
Book Electrician (MM advised not required)
2021-03-01 10:49 · Todo
Order Treatment Tank / Pump Station etc
2021-02-24 15:09 · Todo
RAMS - done 19.02.21 - emailed to Niki
2021-02-22 08:15 · Todo
Final scope of works and sketches agreed with customer
2021-02-19 16:08 · Todo
Introduction email and confirmed date
2021-02-19 15:37 · Michelle · Document
2021-02-19 10:52 · Todo
Book Ground-workers (Dean, Michael and Adam)
2021-02-19 08:46 · Michelle · Document
2021-02-18 15:18 · Todo
N/A Permission to connect to Storm Drain
2021-02-18 15:18 · Todo
N/A Environment Agency - Application
2020-11-06 13:46 · Todo
Post installation visit - within 3 months
2020-11-06 13:46 · Todo
Final email to ensure all has run well & Paperwork
2020-11-06 13:46 · Todo
End of job call to installation lead / Improvement Review