2021-06-09 09:50 · Todo
Final Email to Building Control
2021-05-27 14:41 · Kaz Lumb · Document
2021-05-27 14:41 · Kaz Lumb · Document
2021-05-25 20:29 · Todo
Final email to ensure all has run well & Paperwork
2021-05-25 20:05 · Kaz Lumb · Document
2021-05-25 20:05 · Kaz Lumb · Document
2021-05-25 20:05 · Todo
Advise customer tank service is due
2021-05-25 20:05 · Todo
Post installation visit - within 3 months
2021-05-25 19:04 · Kaz Lumb · Document
2021-05-25 19:03 · Kaz Lumb · Document
2021-05-19 09:38 · Todo
DONE Book Digger, Dumper & Fuel
2021-05-17 08:36 · Todo
Order Concrete, Gravel & Other Bulk
2021-05-17 08:11 · Kaz Lumb · Document
2021-05-17 08:11 · Todo
DONE Book Electrician (Martin MHL)
2021-05-13 13:15 · Todo
Final scope of works and sketches agreed with customer
2021-05-10 10:32 · Todo
Introduction email and confirmed date
2021-04-30 16:47 · Todo
Order Treatment Tank / Pump Station etc (CEN 7 from the farm)
2021-04-30 14:51 · Todo
NA Permission to connect to Storm Drain
2021-04-30 14:51 · Todo
NA Environment Agency - Application
2021-04-14 14:04 · Todo
Order grab lorry/skip for spoil removal
2021-03-16 16:56 · Todo
Order Control Panel - Telemetry - where applicable
2021-03-16 16:56 · Todo
Order Ancillary Materials (pipework etc.)
2021-03-16 16:56 · Todo
End of job call to installation lead / Improvement Review