2026-01-06 09:34 · Todo
Final scope of works and sketches agreed with customer
2022-12-13 15:30 · Todo
Final email to ensure all has run well & Paperwork
2022-12-13 15:30 · Todo
End of job call to installation lead / Improvement Review
2022-12-13 15:30 · Todo
Order grab lorry/skip for spoil removal
2022-12-13 15:30 · Todo
Order Treatment Tank / Pump Station etc
2022-12-13 15:30 · Todo
Order Concrete, Gravel & Other Bulk
2022-11-10 09:25 · Kaz Lumb · Document
2021-12-23 09:05 · Todo
Post installation visit - within 3 months
2021-11-24 14:07 · Todo
Order Ancillary Materials (pipework etc.)
2021-09-29 10:20 · Todo
Introduction email and confirmed date
2021-09-14 13:57 · Todo
Order Control Panel - Telemetry - where applicable
2021-09-14 13:57 · Todo
Waste Transfer Note(s) for any tankering
2021-09-14 13:57 · Todo
Permission to connect to Storm Drain
2021-09-14 13:57 · Todo
Advise customer tank service is due