TPS Group Holdings Ltd - Storage City, Export Drive, Fulwood Industrial Estate, Sutton in Ashfield, Nottinghamshire, NG17 6AF - Carl Smith - Carl.Smith@tpsgroupltd.com - 07894 642 091 - PHASE A (Weekend works), B & C · ☑ Section 106 application, Phase C - Submitted 07/02/2025 - Approved 12/02/2025 - Reminder set near at the time to give a week's notice to Paul Blackmore, Waste Connection Inspector - Pending Section 50-Cad drawing to confirm Phase C start dates
2025-12-10 13:43 · Todo
☑ Section 106 application, Phase C - Submitted 07/02/2025 - Approved 12/02/2025 - Reminder set near at the time to give a week's notice to Paul Blackmore, Waste Connection Inspector - Pending Section 50-Cad drawing to confirm Phase C start dates
2025-11-27 18:07 · Todo
Done - Section 50 application. Phase C - Submitted 04/02/25
TPS Group Holdings Ltd - Storage City, Export Drive, Fulwood Industrial Estate, Sutton in Ashfield, Nottinghamshire, NG17 6AF - Carl Smith - Carl.Smith@tpsgroupltd.com - 07894 642 091 - PHASE A (Weekend works), B & C · Traffic Management, Phase C - Safezone, Garry Ibbertson - 3-way temp traffic lights - Hire duration to be calaculated at a later date - Pending Section 50-Cad drawing to confirm Phase C start dates
2025-11-21 15:36 · Todo
Traffic Management, Phase C - Safezone, Garry Ibbertson - 3-way temp traffic lights - Hire duration to be calaculated at a later date - Pending Section 50-Cad drawing to confirm Phase C start dates
2025-10-15 14:31 · Todo
☑ Introduction email and confirmed date - Phase A: 15th & 16th March - Phase B: 12th May - Phase C: 1st December
2025-09-12 16:52 · Todo
Final email to ensure all has run well, Paperwork - Phase C
2025-09-12 16:52 · Todo
Final email to ensure all has run well, Paperwork - Phase B
2025-09-12 16:52 · Todo
Final Email to Building Control - from the Local Authority
TPS Group Holdings Ltd - Storage City, Export Drive, Fulwood Industrial Estate, Sutton in Ashfield, Nottinghamshire, NG17 6AF - Carl Smith - Carl.Smith@tpsgroupltd.com - 07894 642 091 - PHASE A (Weekend works), B & C · Buildings Control Visit - only applicable for Phase C PAID 17/03/25 - Schedule a visit near at the time - Pending Section 50-Cad drawing to confirm Phase C start dates
2025-09-12 16:52 · Todo
Buildings Control Visit - only applicable for Phase C PAID 17/03/25 - Schedule a visit near at the time - Pending Section 50-Cad drawing to confirm Phase C start dates
2025-09-12 16:52 · Todo
Phase C - Order grab lorry/skip for spoil removal - x2 loads?
2025-09-12 16:52 · Todo
Phase C - Order Tanker - Jetter - to obtain cost locally - Only for Phase C
2025-09-10 09:07 · Todo
☑ Handover info for lead - Phase B - Nothing needs to be ordered - Handed over 09/05/25
TPS Group Holdings Ltd - Storage City, Export Drive, Fulwood Industrial Estate, Sutton in Ashfield, Nottinghamshire, NG17 6AF - Carl Smith - Carl.Smith@tpsgroupltd.com - 07894 642 091 - PHASE A (Weekend works), B & C · ☑ Book Ground-workers - Chris B. & his associate Andy Lowe - Chris B. Invoice for Phase A send to Lee 21/03/2025 - Chris B. Invoice for Phase B send to Lee 22/05/2025
2025-05-22 09:29 · Todo
☑ Book Ground-workers - Chris B. & his associate Andy Lowe - Chris B. Invoice for Phase A send to Lee 21/03/2025 - Chris B. Invoice for Phase B send to Lee 22/05/2025
2025-05-21 10:05 · Todo
☑ Phase B - Book Digger, Dumper & Fuel - Chris supplied most items
2025-05-21 10:05 · Todo
☑ Phase B - Order Ancillary Materials (pipework etc.) - Chris B. supplied most items
2025-05-21 10:05 · Todo
☑ Phase B - Order Concrete, Gravel & Other Bulk - Chris B. supplied most items
2025-05-21 10:05 · Todo
☑ Phase B - Order Tanker - Jetter - to obtain cost locally - Not required at this stage, only for Phase C - Chris B. TBC
2025-05-21 10:04 · Todo
☑ Phase B - Order grab lorry/skip for spoil removal - x2 loads? - Chris B. supplied most items
2025-05-21 08:50 · Todo
☑ 2) Call Chris B. & Andy Lowe to confirm everything is running smoothly
2025-05-14 10:06 · Todo
☑ Handover info for lead - Kit list for Phase A to be collected Friday 14/03/2025
2025-05-14 10:06 · Todo
☑ Final scope of works and sketches agreed with customer
2025-05-14 10:06 · Todo
☑ Phase A, Search before you dig - x2 outstanding: Mbnl & Utility assets - Chased 28/02/2025
2025-05-14 10:06 · Todo
☑ Building Control - Submitted 13/02/2025 - Acknowledgment of application submission 27/02/2025 - Invoice paid: 17/03/2025
2025-03-20 09:45 · Todo
☑ Phase A - Order Ancillary Materials (pipework etc.) - Kit list confirmed
2025-03-20 09:45 · Todo
☑ Phase A - Order grab lorry/skip for spoil removal - Not required at this stage
2025-03-20 09:38 · Todo
☑ Phase A - Order Tanker - Jetter - to obtain cost locally - Not required at this stage, only for Phase C
2025-03-20 09:37 · Todo
☑ Phase A - Order Concrete, Gravel & Other Bulk - Chris to supply
2025-03-20 09:33 · Todo
☑ Phase A - Book Digger, Dumper & Fuel - Chris to supply
2025-03-20 09:05 · Todo
☑ Phase A - Order B125 lids 450mmx450mm - Civils & Lintels - Delivery to MPC
2025-03-20 08:49 · Todo
☑ Final email to ensure all has run well, Paperwork - Phase A
2025-02-05 13:57 · Todo
☑ Commission Certificate - to be retained until final balance is paid - N/A
2025-02-05 13:53 · Todo
☑ Order Control Panel - Telemetry - where applicable - N/A
2025-01-23 09:09 · Todo
☑ Check Sub-Contractors insurance (in date correct level of cover)