2026-01-06 09:35 · Todo
DONE Environment Agency - Application - Chase with Dave Bayliss in March for update
2024-10-08 16:14 · Louise Prince · Document
Dunley Luxury Lodges, The Orchard, Dunley, Stourport-on-Severn, DY13 0TT, Victoriaabayliss@hotmail.com, Danalexsos@btinternet.com, 07940 420 398 - Dave Bayliss, 07940 420 398 · RE_ Request for Further Information for the Water Discharge Activity at Dunley Luxury Lodges Ref_ EPR_BB3356TD_A001 PLEASE RESPO.msg
2024-09-20 08:09 · Michelle · Document
2024-06-27 09:50 · Louise Prince · Document
2024-06-27 09:50 · Louise Prince · Document
2024-01-17 11:37 · Todo
DONE Post installation visit - within 3 months
2023-08-18 11:07 · Todo
DONE Final email to ensure all has run well & Paperwork
2023-07-27 11:01 · Todo
N/A Order Control Panel - Telemetry - where applicable
2023-07-27 10:55 · Todo
N/A Waste Transfer Note(s) for any tankering
2023-07-26 12:06 · Todo
Call customer to check all is well - day one, day three and last day for final call
2023-07-24 13:58 · Todo
DONE Order Ancillary Materials (pipework etc.)
2023-07-20 11:49 · Todo
DONE Final scope of works and sketches agreed with customer
2023-07-13 10:21 · Todo
DONE Order Treatment Tank / Pump Station etc
2023-06-23 16:03 · Todo
End of job call to installation lead / Improvement Review