ISO

Non-Conformance Log

Capture the real picture across safety, quality, environmental, and design. Open items are expected while they are being understood and worked through.

Reset
Status: Resolved13 results
ReferenceLogged DateStatusSite/PartyTitleOwner
NCL-2026-00472026-04-20ResolvedUrgentTesting
testing
Luke Shepherd
NCL-2026-00402026-04-17ResolvedUrgentTesting
Testing
Luke Shepherd
NCL-2026-00232026-04-13ResolvedAll Projects
Project WhatsApp groups
Luke Shepherd
NCL-2026-00202026-04-13ResolvedNo
Text magic not responded to
Rob Preston
NCL-2026-00152026-04-02ResolvedUnited Utilities
UU Whitegates - Parcel ot delivered by DPD
Michael Johnstone
NCL-2026-00142026-04-02ResolvedKingspan
Espais Roca Ltd, LE16 9RF - Shaft Delivered Late
Michael Johnstone
NCL-2026-00112026-03-31Resolved4 Valley View, S26
Tanker unable to access site
Shaun
NCL-2026-00102026-03-31ResolvedSutton Farm Barns
Return trip following service - 30/03/2026
Sophie
LME2026-03-25ResolvedLME
MISTAKES WITH PANEL BUILD AND LACK OF DRAWINGS
Rob Preston
UU Milburn2026-03-16ResolvedEWW
CRX 50 Access pits constructed incorrectly
Rob Preston
NCL-2026-00682026-02-11Resolved/parts/
Fraser Scott SK17 8QP , Perc test , 22/1/26 , asbestos found while excavating test hole 1 by Chris Brittland , job did n
NCL-2026-00032026-02-09ResolvedStroud - Bushy Beeches
Three phase pump was delivered and taken to site
Michelle
NCL-2026-00022026-01-28ResolvedKevin Whitmarsh
Eff ps chamber imploded
Rob Preston